| Referencia(s) |
| Descripción del anverso | The section of the vertical shaft francis turbine, spiral case, runner, distributor and draft tube can be observed. Design of russian origin and each unit with a power of 33 MW. G08 is the power plant code in the energy market in El Salvador. |
|---|---|
| Escritura del anverso | Latin |
| Leyenda del anverso | PROYECTO HIDROELÉCTRICO EL CHAPARRAL - CENTRAL HIDROELÉCTRICA 3 DE FEBRERO |
| Descripción del reverso | The reservoir and the dam of the hydroelectric power plant. |
| Escritura del reverso | Latin |
| Leyenda del reverso | EL SALVADOR 2023 |